At a glance
- Building: Secondary school, including laboratories
- Location: Clydebank, West Dunbartonshire
- Heat source: The school's existing ground loop
- System: Eight 45 kW ground source heat pumps in cascade, natural refrigerant R290 (MasterTherm AQ45IP)
- Capacity: About 360 kW nominal
- Our part: MasterTherm heat pumps and design support
- Completed: 2026
At Clydebank High School, an ageing ground source system was renewed without drilling a single new borehole.
The brief
The school's original ground source plant was reaching the end of its life. Replacing the ground loop as well would have been costly and disruptive.
What was done
The existing 20-year-old ground loop was kept and connected to a new cascade of eight R290 heat pumps. A heat recovery circuit lets the system heat and cool at the same time, including precise chilled water for a laboratory, so heat removed from one part of the school is reused in another. A valve gallery with actuated zone valves distributes heating and cooling around the building.
The result
- No new drilling
- Simultaneous heating and cooling
- Modern R290 plant on existing infrastructure