At a glance
- Building: Secondary school
- Location: Rhondda Cynon Taf
- Heat source: Air
- System: Four air source heat pumps using natural refrigerant R290 (MasterTherm BoxAir BA90IP), with a 1,000-litre buffer
- Controls: BMS integration and heat metering
- Our part: System design, MasterTherm heat pumps and commissioning support
- Completed: February 2026
At Ysgol Nantgwyn, the old heating plant was swapped for four air source heat pumps while lessons carried on.
The brief
Replace end-of-life heating plant with a low-carbon system, without closing the school.
What was done
The heat pumps sit in a new fenced compound outside, connected to the plant room by 110 metres of pre-insulated pipe. The old steel plant was stripped out and the new system was in and running in about a week. It feeds a 1,000-litre buffer, is controlled through the school's BMS, and is heat-metered so its performance can be tracked.
The result
- Fossil-fuel plant replaced with R290 heat pumps
- About a week from strip-out to running
- No disruption to teaching